One of six massive natural gas-fired engines manufactured by Everllence (formerly MAN Energy Solutions) is lifted by crane during the unloading process at the Port of Freeport in Texas. Each engine weighs approximately 540,000 pounds and will help power KPUB's new 122-megawatt generation plant in Colorado County, Texas.

One of six massive natural gas-fired engines manufactured by Everllence (formerly MAN Energy Solutions) is lifted by crane during the unloading process at the Port of Freeport in Texas. Each engine weighs approximately 540,000 pounds and will help power KPUB’s new 122-megawatt generation plant in Colorado County, Texas.

November 23, 2026—Kerrville Public Utility Board (KPUB) is celebrating a major milestone in the construction of its new natural gas-fired power generation plant, as all six of the facility’s massive engines have arrived at the Port of Freeport in Texas following their transatlantic journey from Europe.

Manufactured by Everllence (formerly MAN Energy Solutions), each engine weighs approximately 540,000 pounds. The engines began their journey in Saint-Nazaire, France, where they were loaded and welded directly to the deck of a cargo ship for transport. The vessel then traveled to Antwerp, Belgium, to load six alternators and nearly 50 containers of auxiliary equipment before crossing the Atlantic Ocean to Texas.

“The arrival of these engines is a major milestone for this project. They are some of the most critical pieces of equipment for the entire facility, and having them here in Texas significantly reduces some of the biggest risks associated with manufacturing and transporting equipment of this size,” said Mike Wittler, KPUB General Manager and CEO.

With the engines now in Texas, the project team is preparing for their transportation to the construction site in Colorado County, approximately 10 miles south of Columbus, Texas. The site was selected for its strong infrastructure and proximity to four major natural gas pipelines, resources not readily available in Kerr County. The facility is being constructed adjacent to Sky Global Power One, an existing 50-megawatt natural gas-fired generation plant that achieved 99.6% availability during Winter Storm Uri in 2021.

The new plant will feature six advanced reciprocating internal combustion engines (RICE), capable of producing up to 122 megawatts of dispatchable power. These highly efficient engines can reach full load in less than 10 minutes, operate in extreme temperatures and use virtually no water. Their ability to start quickly and respond to changing market conditions will allow KPUB to generate electricity when prices are high and purchase lower-cost power when prices are more favorable.

Since breaking ground in April 2026, construction has continued to advance, with foundations for all six engines completed, significant progress made on the powerhouse building, major cooling equipment installed, and all three substation transformers delivered and placed on their foundations.

Commercial operations are currently projected for December 1, 2027, later than originally anticipated. The revised schedule reflects construction and project execution challenges as work has progressed, including additional engineering and coordination requirements. KPUB and its project partners continue evaluating the remaining construction and commissioning schedule and identifying opportunities to minimize further delays.

As construction has progressed, KPUB has identified significant project cost increases that will require additional financing. These increases are attributable to several factors, including federal tariffs, rising equipment and material costs, construction labor costs, and additional project scope and engineering requirements identified during construction. Significant data center and industrial development across Texas has increased demand for construction materials and skilled labor, contributing to higher costs.

KPUB is working closely with its development partner, independent engineer and construction contractors to evaluate and negotiate these costs, identify opportunities for savings, and establish a more reliable estimate of the total cost to complete the facility.

 

“While construction costs have increased, we are committed to managing those expenses responsibly while keeping this important project moving forward,” Wittler said. “The reasons we pursued owning our own generation haven’t changed. We remain confident this investment will strengthen our ability to manage power supply costs and maintain competitive electric rates for decades to come.”

KPUB is evaluating additional financing options, including the Texas Energy Fund and revenue bonds, and anticipates bringing a supplemental financing request to its Board of Trustees and the Kerrville City Council in early 2027. More detailed financial information will be provided as remaining construction costs and financing requirements become clearer.

The project remains an important part of KPUB’s long-term strategy to maintain stable, affordable electric rates by providing greater control over power supply costs. While KPUB will remain part of the ERCOT market, owning its own generation, combined with an updated hedging program, is expected to provide customers with additional financial protection from volatile electricity prices, particularly during extreme weather events.

KPUB will continue providing regular updates as construction advances. Additional information about the generation project is available at kpub.com/power.